Two Instance getting triggered on Change of PO for BUS2012

$
0
0

Hello experts,

I have created a single step Workflow, to be triggered on change of PO.

 

I created a Subtype of BUS2012 and delegated it. added a new method to carry out the processing as required.

 

However on change there are two workflow instance in the SWIA, one completed and the other in Error state.

on examining the SWEL, for a change to PO, there are three entries for Change event.

1. BUS2012 - Changed event - No receiver entered

2. BUS2012 - Changed event - receiver found (My task)

3. FREBUS2012 - Changed event - receiver found ( My Task).

4. FREBUS2012 - event is CHANGEFRE - NO receiver entered.

 

 

I have created just one link in SWE2, however I am not able to figure it out why FREBUS2012 is getting a receiver.

 

Please help.

 

Regards,

Jibran