Quantcast
Channel: SCN : Unanswered Discussions - SAP Business Process Management
Viewing all articles
Browse latest Browse all 3160

SM12 SWWWIHEAD

$
0
0

Hello Expert,

 

     I have read some of the post  here about Workflow locking. I just wanted to confirm my understanding. Apologies if its basic, we dont have WF consultant now, so I'm reaching out for help.

 

     We have old entries in SM12 table SWWWIHEAD, upon checking i can see that the WF is still in progress and that a background task is being executed? Is this normal that this will cause locking in SM12?

 

     WF 1.PNG

     The background task is being run every 24 hours.

     WF 2.PNG

 

     Additionally, will SM12 carry the first locking date? As you will notice in SM12 the lock date was June 12, while the background task was created on June 13. Before that the first background task was done on June 12 and is not set to complete.

 

     This is the situation when the 24 hrs background job is running until the WF is completed.


Viewing all articles
Browse latest Browse all 3160

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>